Severe floods devastate state's electricity system; Restoration efforts underway amidst challenges
Severe floods devastate state's electricity system; Restoration efforts underway amidst challenges
The state’s electricity infrastructure has been severely damaged following catastrophic flooding. With engineers, officials, and staff from the Tripura State Electricity Corporation Limited (TSECL) working tirelessly to restore power. Despite round-the-clock efforts, full restoration remains challenging, particularly in the South and Gomati districts, which have been hit hardest by the floods.
TSECL through a press statement said that in the South district, progress has been notable, with electricity re-established in 164 out of 195 Gram Panchayats and Village Committees across Sabroom, Santirbazar, and Belonia.
However, ongoing difficulties include areas without road connectivity and extensive water accumulation that makes it difficult to erect new electricity poles. Efforts are being focused on reconnecting the remaining 31 Gram Panchayats and Village Committees part, with support from both district and sub-divisional administrations.
In the Gomati district, power has been largely restored to Udaipur, though Amtali and Banduar in the Tepania area remain without service due to severe water logging. Additional complications have arisen in Shalagra Beri, Rajdhar Nagar, and Fakirbari where water accumulation continues to obstruct restoration efforts. Most of Udaipur division has regained power except for Purba Mirza Switchgate Para, Radha Banshi Para, and Chhota Gangrai, where service remains interrupted.
The Amarpur division has faced the most severe impacts, with extensive water logging and fallen trees hampering restoration. Despite these obstacles, TSECL workers have successfully reactivated power in many areas. The corporation is in ongoing communication with the Gomati District and Amarpur Sub-Divisional Administrations to expedite service restoration in the affected regions.
As the state battles the aftermath of these unprecedented floods, TSECL remains committed to overcoming the challenges and restoring electricity as swiftly as possible, with continued cooperation from local authorities essential for progress.
NEH Report
Senior Staff Reporter at Northeast Herald, covering news from Tripura and Northeast India.
Related Articles

Tripura govt to move HC to reopen 1996 massacre case: CM Dr Saha
CPIM synonymous with terror, rapist, murderer and suppression: CM

Four women drug peddlers from Bihar and a driver arrested with large quantities of Ganja at Churaibari
Four women drug peddlers from Bihar and a driver arrested with large quantities of Ganja at Churaibari

Tension erupts in Bijaynagar during anti-Ganja operation
At least 20 injured, including women; one youth critically hurt

70 pc of PM Modi's internal security-related directives implemented in Tripura: CM
CM emphasizes pro-people policing to build a better Tripura
Latest News

Chaos and anarchy at Salt Lake Stadium as Messi visit cut short after fan unrest

Messi fever grips Kolkata as football icon unveils 70-foot statue, meets Shah Rukh Khan

Too much social media? Scientists find link to attention loss in kids

Sanskrit returns to Pakistan for the first time since Partition